The builders are in, the electricians are here

At Javelin’s Camberley site, space is being created  and resources being readied to  accommodate the addition of more production equipment. The contractors are here making the necessary resources available to the parts of the factory which have been earmarked for the new production equipment. Over successive weekends,  our printing and  assembly departments have been relocated to a dedicated  area  for  secondary operations. We have now brought these  processes into one space which streamlines the business flow for these products. Next weekend sees the first of the “3 Big Moves” with 24 moulding machines relocating to a new area in the factory. The presses  will  be switched off on Friday evening, moved, reconnected and be ready for start of production on Monday morning.